HOW TO ANALYSE 1 CUM OF BRICK MASONARY IN THE RATIO OF 1:6

Solution:

Given Quantity=1 CUM

Mortar Ratio:1:6

Remember 30% Cement Mortar is Required In Case of Stone Masonary

Motar Required= 30% of 1 CUM

Motar Required= 0.3 X 1 CUM

Motar Required=0.3 CUM

Mortar Ratio=1:6 (Given)

Sum of Ratios=1+6=7

Cement Required=1÷7 X 0.3 CUM

Cement Required=0.043 CUM

Cement Required=0.043 X 28.8

Cement Required=1.24 Bags

Remember 28.8 Bags of Cement Are Required in 1 Cum

Sand Required=6÷7 X 0.3 CUM

Sand Required=0.26 CUM

Labour Productivity

1 Mason,1 Men Mazdoor & 1 Women Mazdoor Can Do 1.25 CUM of Brick Masonary Work Per Day

Labour Statement

Mason Required=0.8 No.

Men Mazdoor=0.8 No.

Women Mazdoor=0.8 No.






No comments:

Post a Comment

If You Have Any Doubt!Please Let Me Know

Featured post

ANALYSE AN RCC SLAB FOR A ROOM MEASURING 1 METRE X 1 METRE HAVING SLAB THICKNESS EQUAL TO 0.15 METRE

Solution: Volume =1 Metre X 1 Metre X 0.15 Metre Volume=0.15 Metre Or, Dry Volume = 0.15 Cubic Metre Wet Volume=Dry Volume X 1.54 ...